it's a proud moment to share with you that, during April - May 2016, Team Ecosyms has Successfully executed the turnkey project of, 33KVA HT Cable laying work of, 465Mtrs, at Kolhapur (Pune - Bangalore National Highway at Ambap Phata).

Horizontal drilling at Service Road, at 20Ft down the ground, crossing the 65 Meter one way Highway line, was a difficult task, as heavy vehicles were moving round the clock, causing heavy vibrations and hard / soft soil condition was always changing the direction of drill bit.Horizontal drilling at Service Road, at 20Ft down the ground, crossing the 65 Meter one way Highway line, was a difficult task, as heavy vehicles were moving round the clock, causing heavy vibrations and hard / soft soil condition was always changing the direction of drill bit.

Well experienced Ecosyms Team has taken this challenge and successfully completed the job in 1 month's period.